Thane [India], September 30: The Mumbai-Ahmedabad Bullet Train project has reached an important construction milestone with the successful launch of its first steel bridge in Maharashtra. The 100-metre-long structure was launched over NH-3, also known as the Nashik Highway, at Dive-Anjur village in Bhiwandi, Thane district, on September 28.
The massive steel bridge weighs around 1,405 metric tonnes and was fabricated at a specialised workshop in Tiruchirappalli, Tamil Nadu, nearly 1,300 kilometres away from the installation site. After fabrication, its components were transported to Maharashtra on trailers, where the bridge was assembled before being moved into its final position.
The construction process involved precision cutting, drilling, welding and painting according to approved designs and specifications. Each batch of steel underwent Ultrasonic Testing to check its quality, while the welders and supervisors involved in the fabrication were certified by international welding experts.
At the Thane site, the bridge was assembled on temporary trestles approximately 17.5 metres above ground level. Engineers used 22 skid arrangements and 54,076 Tor-Shear Type High Strength Bolts to put the structure together. The completed bridge was then pulled into position using an automated system consisting of two hollow jacks, each with a capacity of 150 metric tonnes, along with pre-tensioned Macalloy Bars.
The bridge is approximately 14 metres high and 14 metres wide. Its installation was carried out during night-time traffic blocks on the highway to minimise disruption to motorists. The operation required detailed planning because of the size and weight of the structure and its location above an important highway.
Steel bridges are being used on the Mumbai-Ahmedabad High-Speed Rail corridor at locations where longer spans are required, including crossings over highways, expressways, major rivers and railway lines. According to the Ministry of Railways, 28 steel bridges are planned along the corridor, of which 16 have been completed.
The launch of the bridge also highlights the scale of engineering and logistics involved in India’s high-speed rail programme. Fabricating a large structure in Tamil Nadu, transporting it about 1,300 kilometres to Maharashtra and then assembling and launching it over a busy highway required coordination across multiple stages of the project.
The Mumbai-Ahmedabad Bullet Train corridor is being developed as India’s first high-speed rail project. The latest bridge installation in Thane marks another visible step in the construction of the Maharashtra section of the corridor.